How to Calculate Dyeing Cost in Textile Dyeing Factory Easy Way with Example

Sharing is caring!

Introduction

This article is going to talk about how to calculate dyeing cost in Textile Wet Processing Factory simple way. There are some factors that are involved when calculating dyeing cost in Textile Wet Processing Factory.

  1. Types of chemicals and dyes
  2. Types of fabric used and shade required.
  3. Types of dyeing machines and methods used.
  4. Lab expenditure incurred during shade development
  5. Effluent treatment cost.

In the following examples, you will find an initiative to estimate the cost of the pre-treatment and dyeing process. The data provided here are approximate and are being used only as a guide. This article is shown calculate dyeing cost for knitted fabric and woven fabric.

Textile Dyeing Factory
Figure : Textile dyeing factory

Exercise: Calculate Dyeing Cost

Exercise 1: A textile dyeing factory received an order from a garment manufacturer to dye a knitted fabric of 1000 kg. This company can dyeing 300 kg of fabric on a daily basis. The materials and prices used in the process are listed below in the table 1. If the company works one shift per day, calculate the dyeing cost per kilogram with a 20% profit. The total overhead for a month is Rs. 2,50,000 which includes salaries for other employees, electricity bills, plant rent, and other costs.

S/NItems usedQuantity usedPrice in Rs.
 1.Reactive dye3 kg300 per kg
 2.Reactive dye B6 kg250 per kg
 3.Chemical XYZ8 kg80 per kg
 4.Chemical ABC10 kg150 per kg
 5.Machine operators used8400 per shift
 6.Machine helpers used4200 per shift.
Table 1: Chemical used and their prices

Solution

Step 1: Total shift calculation

  • The total production need to be done= 1000 kg
  • Daily production of the company= 300 kg per shift
  • The total shifts required= Order quantity ÷ daily production= 1000 ÷ 300= 3.33 shifts

Step 2: Labour cost

The number of labours used are, 8 machine operators with the wages of Rs. 400 per shift and 4 machine helper with the wage of Rs. 200 per shift.

  • Labour cost of machine operator = number of labour× total working shifts × wage of per shift= 8× 3.33 × 400= 10,656
  • Labour cost of machine helper= 4× 3.33 × 200= 2,664
  • Total labour cost= machine operator cost+ helper cost= 10,656 + 2,664= Rs. 13,320

Step: 3: calculation of chemical cost

  • Reactive dye= 3× 300= 900
  • Reactive dye B= 6× 250= 1,500
  • Chemical XYZ= 8× 80= 640
  • Chemical ABC= 10× 150= 1500
  • Total chemical cost= (900+1500+640+1500)= Rs. 4,540

Step 4: Calculate overhead cost

Company works for this order only 3.33 shifts. Hence, the overhead costs for 3.33 shifts are,

  • Total overhead cost= Rs. 2,50,000
  • Overhead per day ( 1 shift)= 2,50,000 ÷ 30= Rs.8,333.33
  • Therefore, overhead cost for this order= 8,333.33 × 3.33= Rs. 27,749.99

Step 5: Calculate dyeing cost per kg

  • Total cost= labour cost + chemical cost + overheads= 13,320+ 4,540+ 27,749.99= Rs. 45, 609.99
  • Total cost with 20% profit= 45,609.99 + ( 20% profit of 45,609.99)= Rs. 54,731.99
  • Total dyeing cost/ kg= 54,731.99 ÷ 1000= Rs. 54.73

N.B.: Based on their previous experience, companies/merchanters can estimate the cost of dyeing. The exact cost of dyeing must be calculated after the dyeing process has been completed, based on the chemicals and dyes consumed. For a particular order, the above example shows the total cost based on the consumption of all chemicals.

Example 2: An order from a garment manufacturer for the dyeing of 1,50,000 metres of woven fabric was received by a textile dyeing factory . The average production per shift in the company is 30,000 metres. The materials and prices used in the process are listed below table 2. If the company works one shift per day, calculate the dyeing cost per metre with 15% profit. A monthly overhead charge of Rs. 75,000 is incurred for steam, Rs. 30,000 for power, Rs. 7,000 for transport, Rs. 20,000 for rent, and Rs. 95,000 for other expenses.(Assume company works 26 days per month).

S/NItems usedQuantity usedPrice in Rs.
 1.Dye A40 kg400 per kg
 2.Chemical 170 kg200 per kg
 3.Chemical 220 kg170 per kg
 4.Chemical 360 kg150 per kg
 5.Machine operators used15400 per shift
 6.Machine helpers used7200 per shift.
Table 2: List of Chemical used and their prices

Solution

Step 1: Total shift calculation

  • The total production need to be done= 1,50,000 metres
  • Daily production of the company= 30,000 per shift
  • The total shifts required= Order quantity ÷ daily production= 1,50,000÷ 30,000= 5 shifts

Step 2: Labour cost

The number of labours used are, 15 machine operators with the wages of Rs. 400 per shift and 7 machine helper with the wage of Rs. 200 per shift.

  • Labour cost of machine operator = number of labour× total working shifts × wage of per shift= 15× 5× 400= Rs. 30,000
  • Labour cost of machine helper= 7× 5 × 200= Rs. 7,000
  • Total labour cost= machine operator cost+ helper cost= 30,000+7,000= Rs. 37,000

Step: 3: Calculation of chemical cost.

  • Dye A= 40× 400= 16,000
  • Chemical 1 = 70× 200= 14,000
  • Chemical 2 = 20× 170= 3,400
  • Chemical 3 = 60 × 150= 9,000
  • Total chemical cost= (16,000+14,000+3,400+9,000)= Rs. 42,400

Step 4: Calculation of overhead cost

Company works for this order only 5 shifts. Hence, the overhead costs for 5 shifts are,

  • Total overhead cost= (75,000+30,000+7,000+20,000+95,000)= Rs. 2,27,000 per 26 days
  • Overhead per day ( 1 shift)= 2,27,000÷ 26= Rs. 8,730.77
  • Therefore, overhead cost for this order= 8,730.77 × 5= Rs. 43,653.85

Step 5: Calculate dyeing cost

  • Total cost= labour cost + chemical cost + overheads= 37,000+ 42,400+ 43,653.85= Rs. 1,23,053.85
  • Total cost with 10% profit= 1,23,053.85 + ( 15% profit of 1,23,053.85)= Rs. 1,41,511.93
  • Total dyeing cost/ kg= 1,41,511.93÷ 1,50,000= Rs. 0.94 per metre of fabric.

Conclusion

This is the calculation process for dyeing cost. It is used by textile dyeing factories around the world. If you have any questions about dyeing cost calculation, please let me know below in the comments.

  1. How to Calculate Knitting Cost and Weaving Cost : Easy Process with Proper Example
  2. How to Yarn Cost Calculation in Apparel Industry Easy Way: Merchandising Department
  3. Sewing Thread Consumption Calculation Used in Garments Industry with 2 Popular Method
  4. Calculate Size Wise Order Quantity in Garments Industry : An Easy 3 Steps
  5. Easy Fabric GSM Calculation Formula for Woven Fabric and Knit Fabric with 5 Example
  6. Sewing Thread Consumption Shortcut Easy Formula with 5 Exercise

Sharing is caring!

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.